# Set up new manufacturing capacity
In this article, we take you through the steps to use the Contoso Coffee demo data in how you manage capacity.
## Scenario for the testing work center
You are the production planner at Contoso Coffee. In response to changes on the shop floor, you must set up a new work center, Test Department. The new work center has one machine center, Testing. The new centers must have a capacity calendar for a single shift from 08:00:00 AM to 4:00:00 PM, Monday to Friday.
## Set up the centers and calculate capacity
1. Set up the work center.
 1. Select Search (Alt+Q) in the upper-right corner, enter work centers, and then choose the related link.
 1. Choose the New action, and then fill in the fields as described in the following table.
  Field|Value
  No.|700
  Name|Test Department
  Work Center Group Code|1, Production department
  Direct Unit Cost|3.25
  Unit Cost Calculation|Time
  Flushing Method|Manual
  Gen. Prod. Posting Group|MANUFACT<br><br>Note that this selection depends on your accounting setup and country/region.
  Unit of Measure Code|MINUTES
  Capacity|1
  Efficiency|90
  Shop Calendar Code|One shift
  In the Shop Calendar Code field, select the demo calendar One shift, which defines working hours from 8:00 AM to 4:00 PM, Monday to Friday.
 1. Close the work center card.
1. Set up the machine center.
 1. Select Search (Alt+Q) in the upper-right corner, enter machine centers, and then choose the related link.
 1. Choose the New action, and then fill in the fields as described in the following table.
  Field|Value
  No.|760
  Name|Testing
  Work Center No.|700, Test department
  Direct Unit Cost|3.25
  Flushing Method|Manual
  Gen. Prod. Posting Group|MANUFACT<br><br>Note that this selection depends on your accounting setup and country/region.
  Capacity|1
  Efficiency|90
 1. Expand the Routing Setup FastTab, and then, in the Setup Time field, enter 10.
1. Calculate the machine center capacity calendar.
 1. Choose the Calendar action.
 1. In the Machine Center Calendar page, on the Matrix Options FastTab, set the View by field to Month.
 1. Choose the Show Matrix action.
 1. On the Machine Center Calendar Matrix page, choose the Calculate action.
 1. In the Calc. Machine Center Calendar page, on the Options FastTab, set the Starting Date field to January 01.
 1. Set the Ending Date field to December 31.
 1. On the Machine Center FastTab, in the No. filter field, select 760, Testing.
 1. Choose the OK button. After the batch job finishes, it returns you to the Machine Center Calendar Matrix page.
 1. Choose the Refresh action.
 1. On the line for machine center 760, Testing, drill down into the value in the January column.
On the Calendar Entries page, the daily capacity entries in the Capacity (Total) field are for 480 minutes. This reflects one eight-hour shift for each work day. Also, the Capacity (Effective) field shows 432 minutes. This reflects the 90 percent efficiency rate that you assigned to the machine center.
## Related information
Introduction to Contoso Coffee Demo Data<../contoso-coffee-intro>
Find free e-learning modules for Business Central here<https://learn.microsoft.com/training/dynamics365/business-central>

Copyright (c) Microsoft Corporation. CC BY 4.0, https://creativecommons.org/licenses/by/4.0/; code samples MIT. From https://learn.microsoft.com/en-us/dynamics365/business-central/contoso-coffee/manufacturing/set-up-new-capacity, MicrosoftDocs/dynamics365smb-docs at 46907ac (2026-11-19). Changed: includes filled in, links to this site, and for agents shortened without dropping a fact. https://jonas-paprotka.de/docs/contoso-coffee/manufacturing/set-up-new-capacity/