# Power BI projects app KPIs and measures
> APPLIES TO: Generally available in Business Central 2024 release wave 2.
This page provides a list of all Key Performance Indicators (KPIs) included in the semantic model for the Power BI Projects report.
Explore the list of KPIs below to learn more about how they can help you achieve your business goals.
Each KPI is described, including how it is calculated and what data was used in the calculations.
> TIP
> You can easily track the KPIs that the Power BI reports display against your business objectives. See Track your business KPIs with Power BI metrics<track-kpis-with-power-bi-metrics>.
## Project measures
 #no-of-completed-projects
 #project-count
 #tasks-count
 #invoiced-
 #completed-
 #duration-days
 #realization-
 #realization-variance
### No. of completed projects
Formula
The No. of Completed Projects measure calculates the number of projects where the Complete column is "Yes".
Data Sources
 Job
### Project count
Formula
The Project Count measure counts the total number of projects in the Project table.
Data Sources
 Job
### Tasks count
Formula
The Tasks Count measure counts the number of rows in the Tasks table where the Project Task Type has a value of "Posting".
Data Sources
 Job Task
### Completed (%)
Formula
Completed (%) = #total-usage-cost / #total-budget-cost
Data Sources
 Job Ledger Entry
 Job Planning Line
### Invoiced (%)
Formula
Invoiced (%) = #total-invoiced-price / #total-billable-price
Data Sources
 Job Ledger Entry
 Job Planning Line
### Duration (days)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Duration (Days) measure calculates the number of days between the earliest starting date and latest ending date for a given project in the Project table.
Data Sources
 Job
### Realization (%)
Formula
Realization (%) = #total-billable-price / #total-usage-price
Data Sources
 Job Ledger Entry
 Job Planning Line
### Realization variance
Formula
Realization Variance = #total-billable-price - #total-usage-price
Data Sources
 Job Ledger Entry
 Job Planning Line
## Obsolete project measures
### Actual profit
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
Actual Profit = #total-invoiced-price - #total-usage-cost
Data Sources
 Job Ledger Entry
### Actual profit margin %
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
Actual Profit Margin % = #actual-profit / #total-invoiced-price
Data Sources
 Job Ledger Entry
### Budget profit
Formula
Budget Profit = #total-budget-price - #total-budget-cost
Data Sources
 Job Ledger Entry
 Job Planning Line
### Budget profit margin %
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
Budget Profit Margin % = #total-budget-profit / #total-budget-price
Data Sources
 Job Ledger Entry
 Job Planning Line
## Project ledger measures
 #project-ledger-entry-quantity
 #project-ledger-line-amount
 G/L Account Invoiced Cost<#gl-account-invoiced-cost>
 #item-invoiced-cost
 #resource-invoiced-cost
 G/L Account Invoiced Price<#gl-account-invoiced-price>
 #item-invoiced-price
 #resource-invoiced-price
 G/L Account Invoiced Profit<#gl-account-invoiced-profit>
 #item-invoiced-profit
 #resource-invoiced-profit
 G/L Account Usage Cost<#gl-account-usage-cost>
 #item-usage-cost
 #resource-usage-cost
 G/L Account Usage Price<#gl-account-usage-price>
 #item-usage-price
 #resource-usage-price
 #total-invoiced-costs
 #total-invoiced-price
 #total-invoiced-profit
 #total-invoiced-profit-margin-
 #total-usage-cost
 #total-usage-price
 #total-usage-profit
 #total-usage-profit-margin-
### Project ledger entry quantity
Formula
The Project Ledger Entry Quantity measure aggregates the Qty. column of the Project Ledger Entry table. The sign is then inverted by multiplying by negative one.
Data Sources
 Project Ledger Entry
### Project ledger line amount
Formula
The Project Ledger Line Amount measure calculates the Project Ledger Line Amount by iterating over each Project Ledger Entry and multiplying Quantity by Unit Price (LCY).
Data Sources
 Project Ledger Entry
## Project invoiced cost
### G/L account invoiced cost
Formula
The G/L Account Invoiced Cost calculates the total invoiced cost for G/L accounts used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the entry type is "Sale" and the type is "G/L Account".
Data Sources
 Job Ledger Entry
### Item invoiced cost
Formula
The Item Invoiced Cost calculates the total invoiced cost for items used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the entry type is "Sale" and the type is "Item".
Data Sources
 Job Ledger Entry
### Resource invoiced cost
Formula
The Resource Invoiced Cost calculates the total invoiced cost for resources used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the entry type is "Sale" and the type is "Resource".
Data Sources
 Job Ledger Entry
## Project invoiced price
### G/L account invoiced price
Formula
The G/L Account Invoiced Price calculates the total invoiced price for G/L accounts used in a project. It uses the SUMX function to calculate the line amount for each entry where the entry type is "Sale" and the type is "G/L Account".
Data Sources
 Job Ledger Entry
### Item invoiced price
Formula
The Item Invoiced Price measure calculates the total invoiced price for items used in a project. It uses the SUMX function to calculate the line amount for each entry where Entry Type is Sale and Type is Item.
Data Sources
 Job Ledger Entry
### Resource invoiced price
Formula
The Resource Invoiced Price calculates the total invoiced price for resources used in a project. It uses the SUMX function to calculate the line amount for each entry where the entry type is "Sale" and the type is "Resource".
Data Sources
 Job Ledger Entry
## Project invoiced profit
### G/L account invoiced profit
Formula
G/L Account Invoiced Profit = G/L Account Invoiced Price<#gl-account-invoiced-price> - G/L Account Invoiced Cost<#gl-account-invoiced-cost>
Data Sources
 Job Ledger Entry
### Item invoiced profit
Formula
Item Invoiced Profit = #item-invoiced-price - #item-invoiced-cost
Data Sources
 Job Ledger Entry
### Resource invoiced profit
Formula
Resource Invoiced Profit = #resource-invoiced-price - #resource-invoiced-cost
Data Sources
 Job Ledger Entry
## Project usage cost
### G/L account usage cost
Formula
The G/L Account Usage Cost calculates the total usage cost for G/L accounts used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the entry type is "Usage" and the type is "G/L Account".
Data Sources
 Job Ledger Entry
### Item usage cost
Formula
The Item Usage Cost calculates the total usage cost for items used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the entry type is "Usage" and the type is "Item".
Data Sources
 Job Ledger Entry
### Resource usage cost
Formula
The Resource Usage Cost calculates the total usage cost for resources used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the entry type is "Usage" and the type is "Resource".
Data Sources
 Job Ledger Entry
## Project usage price
### G/L account usage price
Formula
The G/L Account Usage Price calculates the total usage price for G/L accounts used in a project. It uses the SUMX function to calculate the line amount for each entry where the entry type is "Usage" and the type is "G/L Account".
Data Sources
 Job Ledger Entry
### Item usage price
Formula
The Item Usage Price calculates the total usage price for items used in a project. It uses the SUMX function to calculate the line amount for each entry where the entry type is "Usage" and the type is "G/L Account".
Data Sources
 Job Ledger Entry
### Resource usage price
Formula
The Resource Usage Price calculates the total usage price for resources used in a project. It uses the SUMX function to calculate the line amount for each entry where the entry type is "Usage" and the type is "Resource".
Data Sources
 Job Ledger Entry
## Project usage profit
### G/L account usage profit
Formula
G/L Account Usage Profit = G/L Account Usage Price<#gl-account-usage-price> - G/L Account Usage Cost<#gl-account-usage-cost>
Data Sources
 Job Ledger Entry
### Item usage profit
Formula
Item Usage Profit = #item-usage-price - #item-usage-cost
Data Sources
 Job Ledger Entry
### Resource usage profit
Formula
Resource Usage Profit = #resource-usage-price - #resource-usage-cost
Data Sources
 Job Ledger Entry
## Project ledger totals
### Total invoiced costs
Formula
Total Invoiced Costs = G/L Account Invoiced Cost<#gl-account-invoiced-cost> + #item-invoiced-cost + #resource-invoiced-cost
Data Sources
 Job Ledger Entry
### Total invoiced price
Formula
The Total Invoiced Price measure returns the absolute value of #project-ledger-line-amount for entries where Entry Type is Sale.
Data Sources
 Job Ledger Entry
### Total invoiced profit
Formula
Total Invoiced Profit = #total-invoiced-price + #total-invoiced-costs
The measure adds invoiced costs because sale entries normally store costs with a negative sign.
Data Sources
 Job Ledger Entry
### Total invoiced profit margin %
Formula
Total Invoiced Profit Margin % = #total-invoiced-profit / #total-invoiced-price
Data Sources
 Job Ledger Entry
### Total usage cost
Formula
Total Usage Costs = G/L Account Usage Cost<#gl-account-usage-cost> + #item-usage-cost + #resource-usage-cost
Data Sources
 Job Ledger Entry
### Total usage price
Formula
Total Usage Price = G/L Account Usage Price<#gl-account-usage-price> + #item-usage-price + #resource-usage-price
Data Sources
 Job Ledger Entry
### Total usage profit
Formula
Total Usage Profit = #total-usage-price - #total-usage-cost
Data Sources
 Job Ledger Entry
### Total usage profit margin %
Formula
Total Usage Profit Margin % = #total-usage-profit / #total-usage-price
Data Sources
 Job Ledger Entry
## Obsolete project ledger measures
### Actual (total price)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Actual (Total Price) measure sums Total Price (LCY) in the Project Ledger Entry table for entries where Entry Type is Usage, then multiplies the result by -1.
Data Sources
 Job Ledger Entry
### Billable (invoiced price)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Billable (Invoiced Price) measure shows the total invoiced price of billable project entries by calculating the total price (in local currency) in the Project Ledger Entry table and selecting only those entries with an entry type of "Sale", which indicates that the project entry is billable.
Data Sources
 Job Ledger Entry
### Invoiced (total cost)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Invoiced (Total Cost) measure calculates the total cost of all project ledger entries where the entry type is "Sale" in the Project Ledger Entry table.
Data Sources
 Job Ledger Entry
### Invoiced (total price)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Invoiced (Total Price) measure calculates the total price of all project ledger entries where the entry type is "Sale" in the Project Ledger Entry table.
Data Sources
 Job Ledger Entry
### Quantity
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Quantity measure calculates the total quantity of a product or service used in a project by summing the quantity in the Project Ledger Entry table and converting the measure to a positive value.
Data Sources
 Job Ledger Entry
### Total price
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Total Price measure sums Total Price (LCY) in the Project Ledger Entry table.
Data Sources
 Job Ledger Entry
## Obsolete usage measures
 #actual-total-cost
 #gen-journal-usage-total-cost
 #labour-usage-total-cost
 #material-usage-total-cost
### Actual (total cost)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Actual (Total Cost) measure calculates the total cost (in local currency) of all project ledger entries where the type is "Usage" in the Project Ledger Entry table.
Data Sources
 Job Ledger Entry
### Gen. journal usage (total cost)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Gen. Journal Usage (Total Cost) measure sums Total Cost (LCY) in the Project Ledger Entry table where Entry Type is Usage and Type is G/L Account.
Data Sources
 Job Ledger Entry
### Labour usage (total cost)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Labour Usage (Total Cost) measure sums Total Cost (LCY) in the Project Ledger Entry table where Entry Type is Usage and Type is Resource.
Data Sources
 Job Ledger Entry
### Material usage (total cost)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Material Usage (Total Cost) measure sums Total Cost (LCY) in the Project Ledger Entry table where Entry Type is Usage and Type is Item.
Data Sources
 Job Ledger Entry
## Planning line measures
 #planning-line-quantity
 #planning-line-total-cost-lcy
 #planning-line-total-price-lcy
 #total-cost-variance-to-budget
 #total-cost-variance-to-budget-
 G/L Account Billable Costs<#gl-account-billable-costs>
 #item-billable-costs
 #resource-billable-costs
 G/L Account Billable Price<#gl-account-billable-price>
 #item-billable-price
 #resource-billable-price
 G/L Account Billable Profit<#gl-account-billable-profit>
 #item-billable-profit
 #resource-billable-profit
 G/L Account Budget Costs<#gl-account-budget-costs>
 #item-budget-costs
 #resource-budget-costs
 G/L Account Budget Price<#gl-account-budget-price>
 #item-budget-price
 #resource-budget-price
 G/L Account Budget Profit<#gl-account-budget-profit>
 #item-budget-profit
 #resource-budget-profit
 #total-billable-cost
 #total-billable-price
 #total-billable-profit
 #total-budget-cost
 #total-budget-price
 #total-budget-profit
### Planning line quantity
Formula
The Planning Line Quantity measure calculates the sum of the quantity column in the Project Planning Line table.
Data Sources
 Job Planning Line
### Planning line total cost (LCY)
Formula
The Planning Line Total Cost (LCY) measure calculates the total cost of all project planning lines in the Project Planning Line table. It uses the SUMX function to iterate over each row in the table and multiply the quantity and unit cost (in local currency) columns for each row. The results of each multiplication are then summed up to produce the total cost.
Data Sources
 Job Planning Line
### Planning line total price (LCY)
Formula
The Planning Line Total Price (LCY) measure calculates the total price of all project planning lines in the Project Planning Line table. It uses the SUMX function to iterate over each row in the table and multiply the quantity and unit price (in local currency) columns for each row. The results of each multiplication are then summed up to produce the total price.
Data Sources
 Job Planning Line
### Total cost variance to budget
Formula
Total Cost Variance to Budget = #total-usage-cost - #total-budget-cost
Data Sources
 Job Ledger Entry
 Job Planning Line
### Total cost variance to budget %
Formula
Total Cost Variance to Budget % = #total-cost-variance-to-budget / #total-budget-cost
Data Sources
 Job Ledger Entry
 Job Planning Line
## Project billable costs
### G/L account billable costs
Formula
The G/L Account Billable Costs calculates the total billable cost for G/L accounts used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the line type is "Billable" or "Both Budget and Billable" and the type is "G/L Account".
Data Sources
 Job Planning Line
### Item billable costs
Formula
The Item Billable Costs calculates the total billable cost for items used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the line type is "Billable" or "Both Budget and Billable" and the type is "Item".
Data Sources
 Job Planning Line
### Resource billable costs
Formula
The Resource Billable Costs calculates the total billable cost for resources used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the line type is "Billable" or "Both Budget and Billable" and the type is "Resource".
Data Sources
 Job Planning Line
## Project billable price
### G/L account billable price
Formula
The G/L Account Billable Price calculates the total billable amount for G/L accounts used in a project. It uses the SUM function to add up all entries by the Line Amount (LCY) column where the line type is "Billable" or "Both Budget and Billable" and the type is "G/L Account".
Data Sources
 Job Planning Line
### Item billable price
Formula
The Item Billable Price calculates the total billable amount for items used in a project. It uses the SUM function to add up all entries by the Line Amount (LCY) column where the line type is "Billable" or "Both Budget and Billable" and the type is "Item".
Data Sources
 Job Planning Line
### Resource billable price
Formula
The Resource Billable Price calculates the total billable amount for resources used in a project. It uses the SUM function to add up all entries by the Line Amount (LCY) column where the line type is "Billable" or "Both Budget and Billable" and the type is "Resource".
Data Sources
 Job Planning Line
## Project billable profit
### G/L account billable profit
Formula
G/L Account Billable Profit = G/L Account Billable Price<#gl-account-billable-price> - G/L Account Billable Costs<#gl-account-billable-costs>
Data Sources
 Job Planning Line
### Item billable profit
Formula
Item Billable Profit = #item-billable-price - #item-billable-costs
Data Sources
 Job Planning Line
### Resource billable profit
Formula
Resource Billable Profit = #resource-billable-price - #resource-billable-costs
Data Sources
 Job Planning Line
## Project budget costs
### G/L account budget costs
Formula
The G/L Account Budget Costs calculates the total budget cost for G/L accounts used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the line type is "Budget" or "Both Budget and Billable" and the type is "G/L Account".
Data Sources
 Job Planning Line
### Item budget costs
Formula
The Item Budget Costs calculates the total budget cost for items used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the line type is "Budget" or "Both Budget and Billable" and the type is "Item".
Data Sources
 Job Planning Line
### Resource budget costs
Formula
The Resource Budget Costs calculates the total budget cost for resources used in a project. It uses the SUM function to add up all entries by the Total Cost (LCY) column where the line type is "Budget" or "Both Budget and Billable" and the type is "Resource".
Data Sources
 Job Planning Line
## Project budget price
### G/L account budget price
Formula
The G/L Account Budget Price calculates the total budget amount for G/L accounts used in a project. It uses the SUM function to add up all entries by the Line Amount (LCY) column where the line type is "Budget" or "Both Budget and Billable" and the type is "G/L Account".
Data Sources
 Job Planning Line
### Item budget price
Formula
The Item Budget Price calculates the total budget amount for items used in a project. It uses the SUM function to add up all entries by the Line Amount (LCY) column where the line type is "Budget" or "Both Budget and Billable" and the type is "Item".
Data Sources
 Job Planning Line
### Resource budget price
Formula
The Resource Budget Price calculates the total budget amount for resources used in a project. It uses the SUM function to add up all entries by the Line Amount (LCY) column where the line type is "Budget" or "Both Budget and Billable" and the type is "Resource".
Data Sources
 Job Planning Line
## Project budget profit
### G/L account budget profit
Formula
G/L Account Budget Profit = G/L Account Budget Price<#gl-account-budget-price> - G/L Account Budget Costs<#gl-account-budget-costs>
Data Sources
 Job Planning Line
### Item budget profit
Formula
Item Budget Profit = #item-budget-price - #item-budget-costs
Data Sources
 Job Planning Line
### Resource budget profit
Formula
Resource Budget Profit = #resource-budget-price - #resource-budget-costs
Data Sources
 Job Planning Line
## Totals for billables
### Total billable cost
Formula
Total Billable Cost = G/L Account Billable Costs<#gl-account-billable-costs> + #item-billable-costs + #resource-billable-costs
Data Sources
 Job Planning Line
### Total billable price
Formula
Total Billable Price = G/L Account Billable Price<#gl-account-billable-price> + #item-billable-price + #resource-billable-price
Data Sources
 Job Planning Line
### Total billable profit
Formula
Total Billable Profit = #billable-total-price - #billable-total-cost
Data Sources
 Job Planning Line
### Total budget cost
Formula
Total Budget Cost = G/L Account Budget Costs<#gl-account-budget-costs> + #item-budget-costs + #resource-budget-costs
Data Sources
 Job Planning Line
### Total budget price
Formula
Total Budget Price = G/L Account Budget Price<#gl-account-budget-price> + #item-budget-price + #resource-budget-price
Data Sources
 Job Planning Line
### Total budget profit
Formula
Total Budget Profit = #total-budget-price - #total-budget-cost
Data Sources
 Job Planning Line
## Project purchase measures
 #amount-on-po
 #amount-rcvd-not-invoiced
 #outstanding-amt-on-po
 #purchase-order-count
 #quantity-on-po
### Amount on PO
Formula
The Amount on PO measure calculates the sum of the amount (in local currency) column in the Purchases table.
Data Sources
 Purchase Line
### Amount rcvd. not invoiced
Formula
The Amount Rcvd. Not Invoiced measure calculates the total amount of purchases that have been received but not yet invoiced in the Purchases table.
Data Sources
 Purchase Line
### Outstanding amt. on PO
Formula
The Outstanding Amt. on PO measure sums the amount in the Purchases table for outstanding purchase lines linked to projects. The source query includes order and invoice lines where Outstanding Qty. (Base) is greater than zero.
Data Sources
 Purchase Line
### Purchase order count
Formula
The Purchase Order Count measure calculates the total number of purchase orders in the Purchases table. It uses the CALCULATE function to filter the table and returns the distinct count of the "Document No." column for the filtered rows.
Data Sources
 Purchase Line
### Quantity on PO
Formula
The Quantity on PO measure calculates the total quantity of items ordered in the Purchases table. It uses the SUM function to add up all the values in the Quantity (Base) column and returns the result.
Data Sources
 Purchase Line
## Obsolete planning line measures
### Billable (total cost)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Billable (Total Cost) measure calculates the total cost (in local currency) of all project planning lines where the line type is "Billable" or "Both Budget and Billable" in the Project Planning Line table.
Data Sources
 Job Planning Line
### Billable (total price)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Billable (Total Price) measure calculates the total price (in local currency) of all project planning lines where the line type is "Billable" or "Both Budget and Billable" in the Project Planning Line table.
Data Sources
 Job Planning Line
### Budget (total cost)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Budget (Total Cost) measure represents the budgeted cost of resources to be used in a project by calculating the total cost (in local currency) in the Project Planning Line table and selecting only those lines with a line type of "Budget" or "Both Budget and Billable".
Data Sources
 Job Ledger Entry
### Budget (total price)
> NOTE
> This measure is deprecated in Business Central 2025 release wave 2 and is no longer available.
Formula
The Budget (Total Price) measure represents the budgeted price of resources to be used in a project by calculating the total price (in local currency) in the Project Planning Line table and selecting only those lines with a line type of "Budget" or "Both Budget and Billable".
Data Sources
 Job Planning Line
## Project task dates and durations
 #project-task-duration-days
 #project-task-duration-weeks
 #project-task-starting-date
 #project-task-ending-date
### Project task starting date
This calculated column returns the earliest Planning Date from the project planning lines related to the task.
Data sources
 Job Planning Line
### Project task ending date
This calculated column returns the latest Planning Date from the project planning lines related to the task.
Data sources
 Job Planning Line
### Project task duration days
Formula
The Project Task Duration Days measure calculates the duration of a project task in days by finding the earliest and latest planning dates from related Project Planning Lines, then returning the day difference between them.
Data Sources
 Project Planning Line
### Project task duration weeks
Formula
The Project Task Duration Weeks measure calculates the duration of a project task in weeks by taking the earliest and latest planning dates from related Project Planning Lines, then returning the week difference.
Data Sources
 Project Planning Line
## Related information
Track your business KPIs with Power BI goals<track-kpis-with-power-bi-metrics>
Power BI Projects app<projects-powerbi-app>
Built-in Projects reports<project-reports>
Project management overview<projects-manage-projects>
Find free e-learning modules for Business Central here<https://learn.microsoft.com/training/dynamics365/business-central>

Copyright (c) Microsoft Corporation. CC BY 4.0, https://creativecommons.org/licenses/by/4.0/; code samples MIT. From https://learn.microsoft.com/en-us/dynamics365/business-central/projects-powerbi-kpis, MicrosoftDocs/dynamics365smb-docs at 46907ac (2026-11-19). Changed: includes filled in, links to this site, and for agents shortened without dropping a fact. https://jonas-paprotka.de/docs/projects-powerbi-kpis/