# Prod. Order - Precalc. Time (report)
The Prod. Order - Precalc. Time report shows details of the calculated durations for production order routing times.
Durations are based on information in the production order, such as the item, quantity, and due date, and manufacturing data such as the routing and bill of materials (BOM).
The report displays information such as:
 Production order
 Operation number
 Type
 Description
 Starting time
 Starting date
 Ending time
 Ending date
 Input quantity
 Expected capacity need
## Use cases
Helps you plan and schedule production activities by estimating the time needed to complete each production order based on factors such as work centers, machine centers, and routing information.
## Try the report
Try the report here: Prod. Order - Precalc. Time<https://businesscentral.dynamics.com?report=99000764>
> TIP
> If you hold down the Ctrl key while you select the report link, the report opens on a new browser tab. The new tab lets you stay on the current page while you explore the report on the other browser tab.
## Contributors
Microsoft maintains this article. The following contributors provided some or all of its contents.
 Jenn Claridge<https://www.linkedin.com/in/jenn-morton-sabre/> | Vice President, ERP Practice
## Related information
Production report overview</production-reports>
Find free e-learning modules for Business Central here<https://learn.microsoft.com/training/dynamics365/business-central>

Copyright (c) Microsoft Corporation. CC BY 4.0, https://creativecommons.org/licenses/by/4.0/; code samples MIT. From https://learn.microsoft.com/en-us/dynamics365/business-central/reports/report-99000764, MicrosoftDocs/dynamics365smb-docs at 46907ac (2026-11-19). Changed: includes filled in, links to this site, and for agents shortened without dropping a fact. https://jonas-paprotka.de/docs/reports/report-99000764/